One ship option is NOT cheaper to operate

11/9/09

A new report from the Route Partnership suggests that the proposed larger combined passenger and freight vessel will be cheaper to operate than the existing two-ship system, but an initial review of the report shows that they have got their calculations seriously wrong.

Many of the most controversial aspects of the Route Partnership (RP) scheme stem from their decision to replace the existing two ship operation with a single larger combined passenger and freight vessel. This approach makes it more difficult for the passenger facilities to be located in the most logical place (on the side of the harbour close to the bus and train stations and adjacent to the town’s main car park) and it requires the controversial lengthening and rock armouring of two historically important listed piers.

The current operator of the service switched from operating one ship to operating two for hard commercial reasons and has continued to operate successfully this way for the last 20 years. Until recently the RP were unable to justify the decision to go for one ship, but on the 31st July 2009 they published a report by Hart Fenton comparing the operating costs of the proposed new vessel with two possible two-ship options. This report concludes that a single vessel as specified by the RP will be the cheapest to operate, but as with the report into alternative options for locating the passenger and freight terminals, it contains a number of flaws that if properly addressed would reverse the report’s conclusions.

The RP have refused to release the technical annexes that contain the data that the report’s conclusions are based on, but from what is available in the main part of the report we know the following:

1. That they have calculated the cost of fuel for a freight ship to be £252,628/annum when the current freight vessel fuel bill is around £50,000/annum.
2. When assessing the running costs of the SWATH fast ferry the report included operating costs for two return trips a day when only one would be needed to transport current passenger numbers (doubling running costs); the fuel bill for this service would be around £384,000 but the RP’s report contains an amount of £955,634.
3. The report also assumes that the SWATH can only operate in wave heights up to 1m thus seriously restricting its sailing schedule, while in fact it is specifically designed for wave heights up to 4m and would be able to operate through the summer season with few if any disruptions to service.
4. The wage cost figures are also subject to query, not only in total but also in detail. For example on a one ship system all cargo working at Penzance would have to be in overtime; this is a significant cost item when comparing a “one ship” with a “two ship” system. Similarly the RP appear not to have allowed for self maintenance, a significant cost saving when operating a two ship system.

The fuel miscalculations alone are sufficient to eliminate most of the claimed cost advantage of the single ship approach. A more detailed analysis will only be possible when the RP release the full figures on which the report is based, but it is already clear from the above examples that the report that the RP is using to justify the choice of a single larger and more costly vessel is seriously flawed.

The failure to properly assess the costs of the fast ferry is from an economic point of view particularly worrying. With the Isles of Scilly at full capacity for long-stay visitors (and no growth in capacity anticipated) one of the few possible growth areas is in day visitors. The proposed new single combined freight and passenger vessel will be no faster or more comfortable and is unlikely to attract new day visitors. A fast ferry on the other hand is likely to be more comfortable and with a journey time of 1.5 hours (instead of 2.5 hours) will attract valuable new business to the islands.

Hart Fenton Report

Other Stories

20/8/10
Andrew George condemns Option A and the "bullying and intimidation" of its supporters

19/8/10
Secretary of State declines to call in LBC application

11/8/10
Joint appeal for DfT investigation of Route Partnership project

6/8/10
Planning committee chair describes Penzance Harbour process as “absolute shambles”

16/7/10
European Parliament to investigate Pz Harbour scheme

12/7/10
URGENT: Please write to Norman Baker MP

28/6/10
South Pier historic listing elevated to Grade II *

23/6/10
Cllr Hicks guilty of “unreasonable and excessive personal attack”

14/6/10
Golden opportunity to reassess Scilly Link scheme

9/5/10
Tender outcome predictable

4/5/10
Vote to save historic seafront

24/3/10
Object to Option A environment consents

20/3/10
Help us secure a Public Inquiry

17/3/10
Option PZ planning application submitted

9/3/10
Misinformation, threats and false promises win the day

9/3/10
Objectors win letters battle hands down

8/3/10
Planning Committee volt face

7/3/10
Option A support so much “smoke & mirrors”

4/3/10
Public give Option PZ a warm welcome

3/3/10
CPRE object to LBC application for Option A

1/3/10
Town Council rejects Option A again

25/2/10
“Option PZ” should unite community

5/3/10
Planners meet this coming Monday

24/2/10
Put Penzance First

24/2/10
Option A Myths

22/2/10
Council harbour decision making "grossly defective"

8/2/10
Council resubmit application for Listed Building Consent

28/1/10
A sad day for Cornwall Council

25/1/10
English Heritage objection to Option A “still stands”

22/1/10
MP convenes meeting to discuss alternatives to Option A

13/1/10
Business community calls for end to Option A plans - now 30 sign-ons

1/1/10
Campaign continues in 2010

14/12/09
Planning Committee REFUSES application - 669 write to object

10/12/09
Packed meeting sends clear message to planning committee

2/12/09
English Heritage say NO to building on Battery Rocks beach

30/11/09
Planning Committee to meet in Penzance on December 10th & 14th

23/11/09
“RMV White Elephant” or, why two ships are better than one

19/11/09
Deadline for objections extended

16/11/09
Out of control Council circumvents normal planning procedures, makes mockery of local democracy

14/11/09
Friends ask Secretary of State to “call in” harbour proposals

13/11/09
Packed house hears extraordinary history of pier

12/11/09
Tinner Challenges Planners

2/11/09
Complaint of maladministration leading to injustice

28/10/09
New Option A planning applications submitted - YOU MUST OBJECT AGAIN!

22/10/09
Option A: two years of hell!

16/10/09
Isles Council continues its bully-boy tactics

9/10/09
Packed public meeting rejects plan to build on Battery Rocks beach

7/10/09
New planning battle kicks off

1/10/09
Offensive remarks a sign of poor judgement

30/9/09
Public Meeting: St John’s Hall, October 9th at 7:30pm

29/9/09
Friends launch Fighting Fund to defend historic seafront

28/9/09
Cornwall Cabinet decision based on biased and misleading information

13/9/09
Cabinet to consider resubmission of Battery Rocks planning application

11/9/09
One ship option is NOT cheaper to operate

25/8/09
Alternative options report fudges figures to support original scheme

25/8/09
MP says Route Partnership scheme "politically undeliverable"

24/8/09
Route Partnership plan will harm regeneration in Penzance

20/8/09
Public rejects Route Partnership scheme (AGAIN)

12/8/09
A reminder of what we stand for...

30/7/09
Scilly Link unviable from Falmouth

27/7/09
Route Partnership attempt to undermine local democracy - historic seafront still in danger!

7/7/09
Route Partnership continue to promote development on Battery Rocks beach

6/7/09
Meadery site "may" be best option for passenger terminal

5/7/09
Friends comment on draft Alternative Options Appraisal

3/7/09
Breakdown of objections published

12/6/09
Planning application withdrawn

19/5/09
Cornwall Council move to consider alternatives

4/5/09
Route Partnership talk about alternatives

1/5/09
Jubilee Pool association joins fight against harbour development

22/4/09
Planners overwhelmed by objections to Route Partnership plan

22/4/09
Planning permission sought for works depot

15/4/09
Time to talk about alternatives

9/4/09
Planning application to be considered on July 7th

26/3/09
Objections still accepted

16/3/09
Object now to stop Battery Rocks beach development

10/3/09
English Heritage unhappy with Route Partnership scheme

5/3/09
Harbour development planning notices published today

4/3/09
Route Partnership admits to exhibition photomontage error

3/3/09
Route Partnership refuses to meet protesters

2/3/09
Traffic survey reveals advantages of out-of-town freight depot

25/2/09
Route Partnership defy public and submit Battery Rocks planning application

23/2/09
Department of Transport request review of Route Partnership plans

19/2/09
Friends of Penzance Harbour call on Councils to provide political leadership

16/2/09
Call for Scillonians to look again at Route Partnership plans for the Islands

11/2/09
Town Council says "no" to Route Partnership scheme

10/2/09
Elected representatives must reject Route Partnership plan for Penzance

5/2/09
Department of Transport admit there is NO time limit on funding

26/1/09
Friends of Penzance Harbour make formal complaint about exhibition

23/1/09
Massive opposition to plans for Penzance harbour